Finzels Reach

The requirements

Finzels Reach development site in Bristol has a long history within the heart of the city, being founded in 1681 and recently used as a brewery until 1999. In 2017 the site was refurbished which required enlarging the existing waterfront opening by removing the lower part of the existing wall.

The existing opening was required to be enlarged by lowering the bottom steel to below ground level, creating a flush new opening.

With limited ground bearing capacity, the only suitable foundations were two piles caps previously installed for Castle Bridge to be founded on. A late design change to the bridge altered its location into the development, meaning the piles and pile caps were redundant. Limited suitable foundations constrained the temporary works design to provide support locations to the top steel in only two places.

A full 3D analysis of the cantilever RMD Superslim frame, supporting a total load of 500kN, was developed using CADS A3D Max then externally checked. Additional analysis was required on the existing beam as to calculate any anticipated deflection and reduce risk on cracking within the masonry.

The RMD Superslim solution provided suitable space for the demolition works, while also allowing reuse of the existing lower steel. Manually handling was kept to a minimum during installation with the use of mechanical hoists and cherry pickers.

Our solution

Lacus sed viverra tellus in hac. Fermentum leo vel orci porta non pulvinar neque. Tellus in metus vulputate eu scelerisque felis. Amet mauris commodo quis imperdiet massa tincidunt nunc. Mauris rhoncus aenean vel elit scelerisque mauris pellentesque pulvinar.

Phasellus faucibus scelerisque eleifend donec pretium vulputate sapien. Facilisi nullam vehicula ipsum a arcu.

Project gallery