Apple Store, Birmingham

The requirements

Launching their new flagship store in 2016, the Apple Store Birmingham required specialist heavy duty propping to create the open plan, clean, feel synonymous with Apple stores globally.

An existing load bearing wall was required to be removed to create the open plan feel. This structural alteration required new structural steel work to be installed to transfer the load from an existing column bearing on the wall, into a new steel frame.

An RMD Megashor structure was designed to support the 1500kN axial load through the existing column, with a bespoke steel work connection to the existing column.

The solution was successfully delivered on time and provided enough space for all demolition works and enough space to install the new steel frame.

Our solution

Lacus sed viverra tellus in hac. Fermentum leo vel orci porta non pulvinar neque. Tellus in metus vulputate eu scelerisque felis. Amet mauris commodo quis imperdiet massa tincidunt nunc. Mauris rhoncus aenean vel elit scelerisque mauris pellentesque pulvinar.

Phasellus faucibus scelerisque eleifend donec pretium vulputate sapien. Facilisi nullam vehicula ipsum a arcu.

Project gallery